By using this site, you agree to the Privacy Policy and Terms of Use.
Accept
The CapitalThe CapitalThe Capital
Notification Show More
Font ResizerAa
  • Home
  • News
    • Featured
      • Featured Profile
    • Top News
    • Top Stories
  • Business
    • Capital Market
    • Energy
    • Maritime
    • Inside Boardroom
  • Politics
  • International
  • Entertainment
    • Events
    • Highlife
  • Lifestyle
    • Society
  • Opinion
    • Guest Columnists
    • Interview
    • Special Features
    • Special Reports
  • Sports
Reading: Premium Exclusive ! Babatunde Fashola in N166 billion contract mess.
Share
Font ResizerAa
The CapitalThe Capital
  • Home
  • News
  • Business
  • Politics
  • International
  • Entertainment
  • Lifestyle
  • Opinion
  • Sports
Search
  • Home
  • News
    • Featured
    • Top News
    • Top Stories
  • Business
    • Capital Market
    • Energy
    • Maritime
    • Inside Boardroom
  • Politics
  • International
  • Entertainment
    • Events
    • Highlife
  • Lifestyle
    • Society
  • Opinion
    • Guest Columnists
    • Interview
    • Special Features
    • Special Reports
  • Sports
Have an existing account? Sign In
Follow US
BusinessHomepagePolitics

Premium Exclusive ! Babatunde Fashola in N166 billion contract mess.

January 25, 2017 7:04 am
The Capital
Share
SHARE

The Bureau for Public Procurement (BPP) has queried the Minister of Works, Power and Housing, Babatunde Fashola over the award of 10 road and bridge contracts worth N166 billion.

The BPP said the minister and his ministry violated the laws guiding contract awards in Nigeria in the manner they selected contractors for the projects.

The procurement agency is asking Mr. Fashola to explain, among other things, why the costs of some of the projects were inflated and why some were awarded to unqualified firms.
The construction of the roads and bridges, spread across the country, were appropriated for in the ministry’s 2016 budget.

The projects are the rehabilitation of Numan-Jalingo Road awarded to Deux Projects Ltd for N11.7 billion; replacement of substandard bridges along Gusau-Sokoto Road awarded to Triacta Nig. Ltd (N1.01 billion); construction of Ojutu Bridge in Ilobu, Osun State awarded to Halicass Integrated Ltd (N522.2 million); construction of Ohan-Moro Bridge on Ilorin-Igbeti Road awarded to Bonus Nig. Ltd (N942.6 million); and rehabilitation of Abuja-Kaduna Road awarded to CGC Nig. Ltd (N26.9 billion).

Others are rehabilitation of Kaduna-Zaria Road in Katsina State awarded to Arab Contractors Nig. Ltd for N14.8 billon; rehabilitation of Zaria-Kano Road in Kaduna/Kano State awarded to Reynold Construction Nig. Ltd (N69.9 billion); and the construction of Burga-Dull-Mbatill-TadnumGpbiya-Badagari-Gwaranga-Sum, Bauchi State awarded to Rahama Civil Works Nig. Ltd (N10.9 billion).

The construction of Tudun Wuss-Wandi-Wandi-Baraza-Durr-Zumbul-Polchi-Dot-Kwanar Road, Bauchi State awarded to Dalum Construction Nig. at N12.2 billion and the construction of Pankshin-Tapshin-Gambar-Sara-Kai-Gindiri Road in Plateau State awarded to Metropolitan Construction Company Limited at N15.3 billion are also among the contracts slated for award by the ministry.

See also  Oil price hits 18-month high at $58.37

How contracts were awarded

In line with the requirement of the Public Procurement Act, 2007, Mr. Fashola’s ministry had, in a letter dated November 7, 2016, requested the Bureau to issue it Due Process Certificate of “No Objection” for the award of the 10 contracts.

The ministry had earlier in June advertised the projects in some national newspapers as well as the Federal Tenders Journal edition of Monday May 30- June 10, 2016.

An addendum to the advertisement was further placed in the same newspapers and Federal Tenders Journal of Monday June 13-Sunday June 26, 2016.

On July 25, 2016, the prequalification documents were opened in the Conference Room of the ministry in the presence of representatives of prospective contractors, non-governmental organisations, the Nigeria Society of Engineers and some member of the public as well as officials of the ministry.

In line with Part V, Clause 22, Section 4 of the Pubic Procurement Act (PPA) 2007, the Permanent Secretary/Chairman of the Ministerial Tenders Board constituted a Technical Evaluation Committee to evaluate the tenders received from prospective contractors.

The contractors successful in the technical evaluation exercise were “provisionally prequalified”, with their documents forwarded to the Federal Inland Revenue Service (FIRS), and banks for verification.

They were subsequently invited to submit completed financial tender documents.

The ministry then carried out a verification exercise on some of the claims made by bidders in their technical bids.
After the verification exercise, the ministry wrote to the BPP to request certificate of no objection for the recommended contractors.

When PREMIUM TIMES contacted Hakeem Bello, the minister’s spokesperson, he declined comment on the Bureau’s report, saying he does not speak for the ministry but for the minister.

See also  Mr. Money! Former First Bank MD, Bisi Onasanya, Makes A Killing With The Address

A staff of the ministry, who only identified herself as Grace told this newspaper on phone that she was not aware of the report.
Some officials of the works ministry however wondered why the BPP asked the ministry to go through another process of post-qualification of firms after all award processes have been completed.

“What the BPP should have done is to compel the ministry to choose the most qualified contractor with the lowest bids,” an official said. “Allowing for any kind of post-qualifications is like changing the rules in the middle of the game.” Source-PREMIUM TIMES

You Might Also Like

Wike vs Fubara: Two Alternatives Before Tinubu To Solidify His Power In Rivers
Top 10 African Countries with the Cheapest Fuel Prices in April 2026
APC must learn from PDP’s mistakes –Timi Frank
SEC’s big moves to deepen capital market, protect investors
Nigerians Begins Receiving N25k Alert As Federal Government Gives New Update
Share This Article
Facebook Email Print

APC Make U-Turn On Senatorial Primaries List

The All Progressives Congress has made a u-turn on its earlier list…

Government Issues Fresh Update on Sallah Celebration

Saudi Arabia government has announced that Eid Al-Adha will be celebrated on…

Fuel nozzle

BREAKING: No More N1320/Litre, Petrol Price Crashes At Depots Nationwide; New Rates Emerge

The price of petrol at various private depots across Nigeria recorded marginal…

Breaking Grounds: Tunji Alausa Flags Off Landmark Hostel Projects at LASU, YABATECH

● Education Minister leads groundbreaking ceremonies as Lagos institutions infrastructure reform ●FG-backed…

The Senate Beckons: Ogun East Unites Behind Dapo Abiodun

● Many Voices, One Mandate: Ogun Endorses Dapo Abiodun In a powerful…

Follow US

Find US on Social Medias
FacebookLike
XFollow
TelegramFollow
WhatsAppFollow

You Might Also Like

Why Buhari, APC Failed In First Four Years — Senate President Lawan

June 22, 2021

IMF: Economy may contract by 1. 8%

July 20, 2016

FG bans importation of vehicles through land borders

December 6, 2016

Abe dares me, I won’t back his gov bid–Amaechi

February 13, 2018

Categories

  • News
  • Homepage
  • Business
  • Politics
  • Top News
  • Highlife
  • Entertainment
  • Sports
  • Lifestyle
  • Inside Boardroom

About The Capital

We deliver premium coverage of business, politics, lifestyle, entertainment, and society stories shaping Nigeria and beyond. Through credible reporting, insightful features, and engaging digital storytelling, we keep readers informed on the people, trends, events, and conversations driving modern culture and public discourse.
Quick Links
  • About
  • Advertise
  • Contact

Connect with us on Social Media

Facebook X-twitter Whatsapp Envelope

Send us email: [email protected]

© thecapital.ng. All Rights Reserved. Designed by Semasir Connect.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?